Digital Project Gantt Chart                                      
Week Commencing 07/02/2005 14/02/2005 21/02/2005 28/02/2005 07/03/2005 14/03/2005 21/03/2005 28/03/2005 04/04/2005 11/04/2005 18/04/2005 25/04/2005 02/05/2005 09/05/2005 16/05/2005 23/05/2005 30/05/2005 06/06/2005 (End of term)
Introduction week                                      
                                     
Planning of Gantt Chart                                      
                                     
Modular Breakdown of Sections                                      
                                     
Generating Detailed Specifications                                      
                                     
Generating Top-Down Block Diags                                      
                                     
Design Blocks: Clock                                      
                                     
Design Blocks: Switch                                      
                                     
Design Blocks: LED interfacing                                      
                                     
Design Blocks: Bin to Gray Decoder                                      
                                     
Design Blocks: Counter Desgin (5b)                                      
                                     
Design Blocks: Edge Triggered Logic                                      
                                     
Simulation of Design                                      
                                     
Conversion to PCB layout                                      
                                     
Budgeting / Buying Components                                      
                                     
Get PCB made                                      
                                     
Build/Test Clock Circuit                                      
                                     
Build/Test Push Switch Input                                      
                                     
Build/Test LED outputs                                      
                                     
Build/Test Gray Code Converter                                      
                                     
Build/Test 5 bit counter                                      
                                     
Build/Test Edge Triggered Logic Block                                      
                                     
Test the circuit as a whole                                      
                                     
Build the Components into the box                                      
                                     
Demonstration                                      
                                     
                                     
Key   Planned time                            
  Actual Time Spent                          
                                     
Deadlines           Week Date         # Marks
Block Diagram viva voce     3   Friday 4th March 05 10  
Combi block design (report)   5   Thurs 17th March 05 30  
Full Design Simulation Demo 7   Friday 15th April 05 30  
Hardware Demo (+L/B submtd) 11   Friday 13th May 05 30  